NCLT cannot permit modifications or withdrawals of CoC approved resolution plans at the behest of the successful resolution applicant, once the plan has been submitted to it a Supreme Court decision

NCLT cannot permit modifications or withdrawals of CoC approved resolution plans at the behest of the successful resolution applicant, once the plan has been submitted to it a Supreme Court decision


The Supreme Court in Ebix Singapore Pvt Ltd vs Committee of Creditors of Educomp Solutions in which it held that NCLT cannot permit modifications or withdrawals of CoC approved resolution plans at the behest of the successful resolution applicant, once the plan has been submitted to it. The Court held that a resolution plan approved by the committee of Creditors and submitted to the National Company Law Tribunal (NCLT) cannot be modified or withdrawn as it would create another tier of negotiations, which will be wholly unregulated by the statute. The court held that since the 330 days outer limit of the CIRP under Section 12(3) of the IBC, including judicial proceedings, can be extended only in exceptional circumstances, "this open-ended process for further negotiations or a withdrawal, would have a deleterious impact on the Corporate Debtor, its creditors, and the economy at large as the liquidation value depletes with the passage of time." The court said that inordinate delays cause commercial uncertainty, degradation in the value of corporate debtors and makes the insolvency process inefficient and expensive. The NCLT and the appellate tribunal (NCLAT) should therefore, while deciding IBC matters, respect the deadline prescribed by the legislature. "We urge the NCLT and NCLAT to be sensitive to the effect of such delays on the insolvency resolution process. The NCLT and the NCLAT should endeavor, on a best effort basis, to strictly adhere to the timelines stipulated under the IBC and clear pending resolution plans forthwith,” the SC said.

Click here for more details

Report Page