How a 120-Person Design Agency Moved Mid-Buildout Without Losing Billable Hours
Over coffee one morning, a stressed colleague from a mid-size design agency described a nightmare: their lease start date was fixed, contractors had paused work for permit reviews, and leadership wanted everyone moved in by the end of the month. The usual move planners gave reassuring, neat timelines that assumed a finished space. That didn't help. What followed was a practical, real-world sequence of choices, tests, and contingencies that turned a potential two-week blackout into a controlled, mostly overnight transition. This case study breaks down what we did, why it worked, and how you can estimate commercial move duration when construction phases are paused.
The Scheduling Challenge: Why Standard Moving Timelines Break DownStandard moving timelines assume the destination is ready - built, fitted, inspected, and cleaned. In our case none of that was guaranteed. Key facts:

Classic move vendors recommended a full-weekend move, staging, or a complete-decommission of the old office. Those plans ignored the reality that finishing trades might restart without notice or that inspection failures could force rework. We needed a plan that matched the actual, paused construction phases and reduced dependence on optimistic contractor timelines.
A Staggered Move Strategy: Aligning Teams with Paused Construction WindowsWe chose a staggered move anchored to construction pauses and to permit-based partial occupancy. The guiding idea was simple: move teams into finished, inspected portions of the space in short, controlled waves, while keeping sensitive operations (server room, client meeting rooms) offline until all inspections were cleared. That reduced risk and limited the maximum exposure to interruptions.
Key elements of the strategy Partial occupancy focus - occupy fully inspected areas first. Staging and storage - temporary storage for furniture and crates in a secured, climate-controlled unit so trades could finish sections without moved-in assets in the way. IT-first test runs - install and validate critical infrastructure in mock setups before the main move. Short burst moves - schedule 24-48 hour moves for specific teams during contractor pauses, not a single massive move. Strict change control - any contractor restart required a 48-hour notice to move teams or shift schedules.That approach accepted that the buildout would be imperfect at move-in and turned the pause into an operational advantage - predictable windows for safe transitions.
Step-by-Step Implementation: How We Synchronized Moves With Construction PausesBelow is the exact sequence we used, with estimatorflorida.com timing and responsibilities. For any commercial move of similar size, this sequence serves as an operational template.
Phase A - Two months out: mapping the finish line Walkthrough with contractor, architect, landlord, IT, facilities, and a senior move coordinator. We created a “finish map” showing which areas would be ready, which needed delay, and what would require protective coverings. Obtain partial certificate of occupancy criteria from the city and landlord. That determined which floors could legally host staff. Identify priority teams: client-facing, servers, and production staff. Those groups required the most reliable environment. Reserve vendor capacity - movers, riggers, and IT installers were booked with flexible date windows instead of fixed dates. Phase B - Four weeks out: test infrastructure and decant planning IT built a mock workstation stack in a small finished area to validate network, security, and VoIP paths. This produced the first measurable uptime metrics. Set up a temporary on-site staging zone and a nearby storage unit for excess furniture. We calculated storage costs vs. the risk of trade damage and opted to store 30% of desks until final finishes. Create individual move packs for every employee - labeled boxes with essentials. That cut unpacking time and limited pileups during short moves. Phase C - Two weeks out: schedule aligned to contractor pause windows We requested the contractor provide written pause windows - times when no subcontractors would be present. Even a tentative 48-hour window is valuable. Vendors received provisional move dates based on those windows. We negotiated break clauses in mover contracts so dates could shift with 72-hour notice without penalties. Emergency mitigation plan drafted: if inspections failed, we would delay non-essential moves and redirect staff to remote work with enhanced schedules for IT to support hybrid onboarding. Phase D - Move execution: controlled, staged transitions Day -1: Movers delivered crates to staging area; IT installed network drops in partial-occupancy zones; essential meeting rooms prepped. Day 0-1: First wave - 40-person client services team moved overnight into the inspected first floor. Movers worked in blocks of 4-hour shifts to minimize noise during critical IT cutovers. Day 2-3: Validation and decongestion - we monitored systems and handed over the floor. Some furniture remained in storage pending final floor finishes upstairs. Day 7: Second wave - creative studio moved during another contractor pause for two days. Nonessential staff continued remote work. Checklist used during execution Permit and partial occupancy verification Vendor arrival windows and contact list Equipment and asset inventory with photographs Floor protection plan for unfinished flooring Emergency contact for site supervisor and landlord From 12-Day Downtime Risk to 48-Hour Business Continuity: Measurable Results in 3 MonthsWe tracked performance against three metrics: downtime (lost billable hours), cost overruns related to rework or damage, and employee disruption (hours spent unpacking and troubleshooting). The results after the two-wave staggered approach were concrete.
Metric Baseline Risk/Estimate Actual After Strategy Maximum potential downtime 12 days (if move and construction clashed) 48 hours for first wave, 48 hours for second wave Billable hours lost (projected) ~1,920 hours (120 people x 8 hours x 2 days x contingency) ~320 hours (first 2-day waves combined; most staff remote for only one day) Direct extra costs (storage, protective materials) Estimated $42,000 $27,500 (saved by staging and selective storage) Rework or damage incidents Potential - several thousand dollars $1,800 (minor scuffing covered by contractor)Key financial takeaways: the staggered approach cut projected lost billable hours by about 83% and reduced expected extra costs by roughly 35%. Critically, it preserved client delivery timelines during the move window.
5 Practical Lessons for Moving During Construction PausesThese are the operational lessons we extracted, each tested in the field.
1. Treat paused construction phases as schedule units, not as failuresPause windows are predictable if you ask for them. Contractors often plan pauses for inspections or materials; obtain written pause windows and build moves around them. That converts uncertainty into scheduling blocks you can plan against.
2. Use partial occupancy to your advantagePartial certificates of occupancy are common. Legally occupying one floor while trades finish another reduces pressure on contractors and avoids forcing a high-risk full move into a half-finished building.
3. Estimate move duration with per-workstation mathOur practical formula for moving timeframe estimate:
Base workstation move time: 45-90 minutes (labeling, packing, transport, basic setup) IT reconnection per workstation: 30-60 minutes (depends on complexity) Multiply by groups you can move in parallel. With two mover crews, you can halve elapsed time but not total crew-hours.Example: 40 workstations with two mover crews and two IT crews = estimated elapsed move time roughly 24-36 hours for that wave, plus validation time.
4. Demand traction from contractors via written commitmentsBe cautious about verbal promises. Insist on written pause/return notifications, and add simple penalties or holdbacks for missed commitments if the landlord contract permits. This isn't about conflict; it's about predictability for payroll and client commitments.
5. Build remediation and remote-work contingenciesHave a robust remote onboarding plan. In our case, non-essential staff worked remotely with staggered return schedules. That flexibility reduced pressure on movers and contractors, and made the staged approach feasible.
How Your Office Move Can Use Paused Construction to Cut Time and RiskBelow are practical steps you can apply immediately to align a move with paused construction phases.
Step 1: Map readiness, not assumptionsGet the contractor and architect to draw a clear map of what is 100% completed, what has pending inspections, and what will definitely change. Use that map to identify safe zones for move-in.
Step 2: Calculate realistic moving timeframe estimatesUse the per-workstation math above, then add buffers: 15-25% for unexpected site navigation issues, plus 2-4 hours per elevator reservation if multi-floor moves require staged elevator use. For client-facing teams, plan two overlapping waves instead of one large wave.
Step 3: Negotiate flexible vendor contractsAsk movers and IT vendors for date flexibility with capped penalties. A 72-hour reschedule window is reasonable. Avoid flat refusal clauses that lock you into a move date when construction remains uncertain.
Step 4: Protect assets and schedule tradesWhere the flooring or painting is incomplete, store desks and sensitive equipment off-site. Where you must move into unfinished areas, buy floor and furniture protection. Coordinate trades to avoid overlapping noisy work during IT cutovers.

Mock up a server and a small cluster of workstations to validate network, security credentials, and printing. That reduces early-day firefighting and gives IT a measured estimate for full rollout time.
Thought experiments to test your plan What if inspections fail two days before your move? - Shift the non-critical wave to remote work, and move the critical team into the inspected zone. Have a small portable office kit for the leadership team to remain on-site if needed. What if the contractor restarts unexpectedly during your move? - Have a site supervisor clause requiring 48-hour notice before noisy trade resumption. If trade resumption happens, movers pause and secure assets until re-permission. What if a mover cancels? - Maintain contact with a backup vendor and keep partial storage access so you can stagger remaining moves rather than rescheduling the entire operation.Moving into a partially finished buildout is stressful but manageable. The core insight is to stop trying to force a perfect single-day move and instead plan around real, verifiable construction pauses. That converts uncertainty into short, manageable operational windows. Applied carefully, the approach preserves billable hours, reduces rework, and keeps employee disruption low.
Final practical checklist before you commit Obtain and verify partial occupancy requirements Secure written contractor pause windows and notification procedures Book movers and IT with flexible date clauses Stage sensitive assets off-site if finishes are incomplete Run a 24-hour IT mock to validate network and security Prepare an employee move pack and communications plan Plan two or more short waves rather than a single all-hands moveWe arrived in the new office with systems working, clients unaffected, and only a handful of minor finish issues to resolve. The most valuable shift wasn't technical. It was the mindset: accept paused construction as a scheduling tool, design moves to fit those pauses, and protect the parts of the business that cannot tolerate downtime. That combination made what seemed impossible entirely practical.