DPR
@SerawitGood morning :-11/07/2013
Obora- Sidan- Tuluwayu Road Project;
Daily Work progress:-
Working Station from 3+300-22+240
-Common Excavation=1928.00m3 with Ex.9:40hr & Dzr. 8:00 hr
-Common slope trimming=671.25m3 with Ex.8:30 hr
Intermidate slope trimming=320.00m3 with Ex,5:40hr
Intermidate Excavation=2074.00m3 with Ex. 7:40hr & Dzr,with 15:20hr
-Mixing & placing=616.00m3 with Gr, 6:00 hr
Road bed preparation=40.00m3 with Gr, 0:30hr
Under cut Excavation=1540.00m3 with Ex,12:30
Dumping waste=307.00 trip
Linton work for Eng. House=0.00m3
HCB work for Eng. House=0.00m2
Pipe production (Dia. 48)=5.00pcs
Pipe Reinforcement (Dia. 48)=9.5 Cage
Executed amount=1,662,580.00birr
Cost Expense=470,606.64birr
Planned with Avail. Resource=1,579,508.34birr
Accomp. With Available Resource=105.26%
Cost vs. revenue=28.31%
Machinery Status :- Dozer=5(1down),Grader=1, Excavator=5, Loader=2 , D.T=13(4 down), Fuel truck =1,Water truck =2(2Idle Rain case), Vibratory Roller= 2(1 Idle AD), Service vehicle =5, Isuzu cargo=1
Machinery Shortage:-
Dozer (1)
Excavator with jack hammer(1),
Excavator with bucket (1),
Wheel loader (1)
Walk Behind compactor (1),
Fuel truck (1), For buck up
Diesel Generator for crusher(1)
Concrete mixer 350lit(1), leg operated
Water truck (2)
Dump truck (2), replacement
Manpower shortage:-
Senior lab technician (1)
Structure Forman (1),
Plumber (1),
Quantity Surveyor (1)
Store keeper(1)
Material shortage:
*Fuel= 50,000lit
*OPC Cement = 400 qtl
*Aggregate 02=5 trucks
*Pipe molds dia 48"=6pcs
*Matress, Pillow, Blanket, bed sheet, WC for camp service.
Maintenance (Down Own Equipments)
-Komatsu dozer (Engine problem) waiting for inspection mechanic from HO
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-2 Wheel loaders tip
-Fuel truck (Servo,Clutch disk)
-Rivo pick Up (shock absorver)
-Kobelko excavator (Fuel tanker Cup )
-Roller (Vibrator Solenoid and pump )
-1Dump trucks tyre (10pcs)
Bottleneck Resources:
*Excavator with Jack hammer
*OPC Cement
*02 Concrete Aggregate
*Unskilled labour /DL/shortage, Waiting from teltele project
*Water truck for site structure work
Critical issues:
*Bridge investigation Crew mobilization,
*HIV Subcontractor mobilization
*Traverse and differential data compleetion , waiting for Chief surveyor.
Critical material stock Balance:
Fuel=21,228.25Lit, OPC cement=0.00 Qtl, PPC cement=100.00 Qtl, Sand=320.00m3,Aggregate 02=14.00m3