@SerawitGood morning :-10/06/2013
Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-
Working Station from 1+820-43+700
-Common Excavation=5223.19.00m3 with Ex. 30:00 hr & Dz.13:00 hr
-Common slope trimming=795.00m3m3 with Ex.11:00 hr
-Clearing & Grubbing=3.60 hect. With Dzr 16:00 hr
-Mixing & placing=742.00m3 eith Gr. 11:30 hr
-Road bed preparstion=0.00m3 with Gr. 0:00 hr
-Borrow material Prod.=400.00m3 with Ex. 4:00 hr
Dumping waste=181.00 trip
Concrete work for column Eng. House=0.67 m3
Excavation for pipe culvert=4.25m3
Executed amount=2,104,165.60birr
Cost Expense=425,714.05birr
Planned with Avail. Resource=1,957,266.07birr
Accomp. With Available Resource=107.51%
Cost vs. revenue=20.23%
Machinery Status :- Dozer=5(1Down(Own)) ,Grader=1(partial down),Excavator=5(2partial down), Loader=1, D.T=13(6 down), Fuel truck =1,Water truck =2(2AD), Vibratory Roller= 2 (1Down&1AD), Service vehicle =4(1 Down own), Isuzu=1(down,rental)
Machinery Shortage:-
Wheel loader(2)
Excavator with jack hammer(1),
Dozer (1)
Excavator(2),
Walk behind compactor (1),
Small Service Vehicle (1)
Fuel truck (1), For buck up
ISUZU Bus (1)
Manpower shortage:-
Supper Intendent (1)
Structure Forman(2),
Equipment Maintenance Forman(1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth work Forman (1)
Material shortage:
*OPC Cement = 300 qtl
*Aggregate 02=62m3
*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance
*General staff Bed, Blanket,WC for camp service.
Maintenance (Down Own Equipments)
-Double cab pick up (Gear and lock problem)
-Roller (vibrator and pump )
-750 lit Concrete mixer -Motor support
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Maintenance mechanic (for fuel truck dispensor counter error in counting),
Bottleneck Resources:
*Cement
*HCB
*Bar benders and unskilled labour shortage, project is working hard on it.
*Shortage of loaders, As we are obliged to use dozer for waste pushing
*Jack hammer, it is hurting work continuity of stretches
*Fuel Supply interruption
Critical issues:
*Installation of 2nd fuel tanker,
*Bridge investigation Crew mobilization, the two bridges are now accessible
*HIV Subcontractor mobilization
Critical material stock Balance:
Fuel=31,727.86lit , OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=48.00m3,Aggregate 02=56.00m3