English
A specific problem that causes delays to a whole process is called a bottlenecks
The amount of work that can be dealt with in a particular time a period is the throughput
Actual output divided by potential output is capacity utilization
A product that serves its intended function, without any extra features, is described as fit for purpose
If a product has good quality in relationship to its price then it is good value for money
The characteristic of "always working well" is reliability
The characteristic of "lasting a long time" is a durability
A fault in the way something is made is a defect
------
Конкретная проблема, которая вызывает задержки для всего процесса, называется узким местом
Объем работы, которая может быть решена в конкретный период времени, - это пропускная способность
Фактический выход, деленный на потенциальную мощность, - это использование мощности
Продукт, который выполняет свою предполагаемую функцию без каких-либо дополнительных функций, описывается как цель
Если у продукта есть хорошее преимущество в отношении к его цене, то это хорошее соотношение цены и качества
Характерной особенностью «всегда хорошо работает» является надежность
Характерной чертой «долгое время» является долговечность
Ошибка в том, как что-то делается, является дефектом
6.2
planning - 3
scheduling - 5
loading - 1
sequencing - 6
dispatching - 2
monitoring - 4
----
6.4
lead time - time required from receiving a customer order to final delivery; it includes order processing, pre-pack time, in- transit time, receiving and inspection
cycle time - time between one job batch finishing and the next one beginning (includes time taken to prepare machinery for the new process)
downtime - when equipment (or the whole line) stops working and production is lost
changeover time - time taken for a given job/batch to pass through all the operations needed
Overtime - extra hours that someone works. beyond their contractual obligation (and often paid at a higher rate)
set-up time-time taken to prepare machinery and equpment for a new job /batch
lag time- any period of delay between one event and another (eg between giving an instruction and the operation beginning)
time-to-market - time required from the initial concept for a new product to when it first goes on sale
6.5