Good morning :-10/07/2013 

Obora- Sidan- Tuluwayu Road Project;

 Daily Work progress:-


Working Station from 15+200-22+240


-Common Excavation=5404.00m3 with Ex.10:40hr & Dzr. 33:00 hr

-Common slope trimming=422.500m3 with Ex.6:00 hr

Intermidate slope trimming=510.40m3 with Ex,9:20hr

Intermidate Excavation=185.50m3 with Ex. 2:30hr & Dzr,with 0:00hr

-Mixing & placing=868.00m3 with Gr, 7:30 hr

Under cut Excavation=1260.00m3 with Ex,12:50

Dumping waste=272.00 trip

Linton work for Eng. House=0.00m3

HCB work for Eng. House=0.00m2

Pipe production (Dia. 48)=0.00pcs

Pipe Reinforcement (Dia. 48)=9.50 Cage

Executed amount=2,005,056.00birr

Cost Expense=577,274.07birr

Planned with Avail. Resource=1,900,591.67birr

Accomp. With Available Resource=107.83%

Cost vs. revenue=28.79%


Machinery Status :- Dozer=5(1down),Grader=1, Excavator=5(1partial down), Loader=2 , D.T=13(3 down), Fuel truck =1,Water truck =2(2Idle Rain case), Vibratory Roller= 2(Idle AD), Service vehicle =5, Isuzu cargo=1


Machinery Shortage:-


Dozer (1)

Excavator with jack hammer(1),

Excavator with bucket (1),

Wheel loader(1)

Walk Behind compactor (1), 

Fuel truck (1), For buck up

Diesel Generator for crusher(1)

Concrete mixer 350lit(1), leg operated

Water truck (2)


Manpower shortage:-


Senior lab technician (1)

Structure Forman (1),

Plumber (1), 

Quantity Surveyor (1)

Cook (1)

Store keeper(1)



Material shortage:

*OPC Cement = 200 qtl

*Aggregate 02=5 trucks

*Pipe molds dia 48"=6pcs 

*Matress, pillow, Blanket, bed sheet,WC for camp service.



Maintenance (Down Own Equipments)

-Komatsu dozer (Engine problem) waiting for mechanic from HO


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)

-2 Wheel loaders tip 

-Fuel truck (servo,clutch disk)

-Rivo pick Up (shock absorver)

-Kobelko excavator (Fuel tanker cup & Fuel pump)

-Roller (Vibrator Solenoid and pump )

-1Dump trucks tyre (10pcs)


Bottleneck Resources:


*Excavator with Jack hammer 

*OPC Cement 

*02 Concrete Aggregate

*Unskilled labour /DL/shortage, Waiting from teltele project



Critical issues: 

*Bridge investigation Crew mobilization,

*HIV Subcontractor mobilization

*Traverse and differential data not completed, waiting for Chief surveyor.



Critical material stock Balance:


Fuel=26,543.25Lit, OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=320.00m3,Aggregate 02=14.00m3