Obora- Sidan- Tuluwayu Road Project;
Daily Work progress:-
Working Station from (
-Common Excavation=2,699.60.00m3 with Ex. 21:30hr & Dzr. 4:30 hr
-Common slope trimming=343.79m3 with Ex.6:10hr
Intermidate Excavation=2660.00m3 with Ex,27:00
-Mixing & placing=770.00m3 with Gr, 10:05 hr
Dumping waste=224.00 trip
HCB work for Engineers house=83.00m2
Masonary work for outlet (pipe culvert)=1.054m3
Pipe Reinforcement (Dia. 48)=12.5 Cage
Executed amount=1,723,021.60birr
Cost Expense=462,538.81 birr
Planned with Avail. Resource=1,800,408.33birr
Accomp. With Available Resource=95.70%
Cost vs. revenue=26.84%
Machinery Status :- Dozer=5(1down own)(1partial down),Grader=1, Excavator=5(1down), Loader=2(1down), D.T=13(2down)(2partial down), Fuel truck =1,Water truck =2(1partial down), Vibratory Roller= 2 (2partial idle, AD), Service vehicle =5, Isuzu cargo=1, Isuzu Bus=1
Machinery Shortage:-
Wheel loader(1)
Excavator with jack hammer(1),
Walk Behind compactor (1),
Diesel Generator for crusher(1)
Manpower shortage:-
*Project Finance Head (1)
*Plumber (1),
*Earth Work Forman (1)
*Senior lab technician (1)
*Chief cook (1)
*Office engineering head (1)
Material shortage:
*Black wire 1.5mm
*Rebar Dia 8 & dia 6, for pipe production
*OPC Cement = 440 qtl
*Aggregate 02=7 trucks
*Pipe molds dia 48"=6pcs,only 5 molds
*Blanket, Matress ,WC for camp service.
Maintenance (Down Own Equipments)
-Koblelko excavator (Fuel tanker cup & Fuel pump)
-Wheel loader (Service elements)
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-Roller (Vibrator solenoid & pump)
Bottleneck Resources & Affected Activities by these resources:
*OPC Cement -Pipe production & Consultant house
*02 Concrete Aggregate- Pipe production & Consultant house
*Unskilled labour /DL/shortage - over all structure works
*Excavator with Jack hammer - Earth work interruption for section completing.
*RC pipe supply ,100m.- to complete 0+000-11+100 Section structures.
Critical issues:
*Bridge investigation Crew mobilization.
*HIV/STD subcontractor mobilization.
Critical material stock Balance:
Fuel=62,052.05 Lit (Received 46,097.06 Lit), OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=144.00m3,Aggregate 02=0.00m3