Good morning :-24/06/2013 

Obora- Sidan- Tuluwayu Road Project;

 Daily Work progress:-

 

Working Station from (


-Common Excavation=2,699.60.00m3 with Ex. 21:30hr & Dzr. 4:30 hr

-Common slope trimming=343.79m3 with Ex.6:10hr

Intermidate Excavation=2660.00m3 with Ex,27:00

-Mixing & placing=770.00m3 with Gr, 10:05 hr

Dumping waste=224.00 trip

HCB work for Engineers house=83.00m2

Masonary work for outlet (pipe culvert)=1.054m3

Pipe Reinforcement (Dia. 48)=12.5 Cage

Executed amount=1,723,021.60birr

Cost Expense=462,538.81 birr

Planned with Avail. Resource=1,800,408.33birr

Accomp. With Available Resource=95.70%

Cost vs. revenue=26.84%


Machinery Status :- Dozer=5(1down own)(1partial down),Grader=1, Excavator=5(1down), Loader=2(1down), D.T=13(2down)(2partial down), Fuel truck =1,Water truck =2(1partial down), Vibratory Roller= 2 (2partial idle, AD), Service vehicle =5, Isuzu cargo=1, Isuzu Bus=1


Machinery Shortage:-


Wheel loader(1)

Excavator with jack hammer(1),

Walk Behind compactor (1), 

Diesel Generator for crusher(1)


Manpower shortage:-


*Project Finance Head (1)

*Plumber (1), 

*Earth Work Forman (1)

*Senior lab technician (1)

*Chief cook (1)

*Office engineering head (1)


Material shortage:


*Black wire 1.5mm

*Rebar Dia 8 & dia 6, for pipe production

*OPC Cement = 440 qtl

*Aggregate 02=7 trucks

*Pipe molds dia 48"=6pcs,only 5 molds 

*Blanket, Matress ,WC for camp service.


Maintenance (Down Own Equipments)


-Koblelko excavator (Fuel tanker cup & Fuel pump)

-Wheel loader (Service elements)


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)


-Roller (Vibrator solenoid & pump)


Bottleneck Resources & Affected Activities by these resources:


*OPC Cement -Pipe production & Consultant house

*02 Concrete Aggregate- Pipe production & Consultant house

*Unskilled labour /DL/shortage - over all structure works 

*Excavator with Jack hammer - Earth work interruption for section completing.

*RC pipe supply ,100m.- to complete 0+000-11+100 Section structures.


Critical issues: 

*Bridge investigation Crew mobilization.

*HIV/STD subcontractor mobilization.


Critical material stock Balance:


Fuel=62,052.05 Lit (Received 46,097.06 Lit), OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=144.00m3,Aggregate 02=0.00m3