DPR

DPR

@Serawit

Good morning :-23/06/2013 

Obora- Sidan- Tuluwayu Road Project;

 Daily Work progress:-

 

Holiday 

Working Station from 9+800-22+220


-Common Excavation=400.00m3 with Ex. 3:00hr & Dzr. 0:00 hr

-Common slope trimming=558.52.00m3 with Ex.8:30hr

Intermidate slope trimming=264.06m3 withEx,5:00hr

Intermidate Excavation=1248.00m3 with Ex,13:00

-Mixing & placing=630.00m3 with Gr, 5:30hr

Dumping waste=107.00 trip

HCB work for Engineers house=100.00m2

Masonary work for outlet (pipe culvert)=0.86m3

Pipe production (Dia. 48)=3.00pcs

Pipe Reinforcement (Dia. 48)=11.50 Cage

Executed amount=689,752.08birr

Cost Expense=322,596.10birr

Planned with Avail. Resource=794,850.00birr

Accomp. With Available Resource=86.78%

Cost vs. revenue=46.77%


Machinery Status :- Dozer=5,Grader=1, Excavator=5(1partial down,1down), Loader=2(1down), D.T=13(4down)(5partial down), Fuel truck =1,Water truck =2(1partial down), Vibratory Roller= 2 (2partial idle, AD), Service vehicle =5, Isuzu cargo=1, Isuzu Bus=1


Machinery Shortage:-


Wheel loader(1)

Excavator with jack hammer(1),

Dozer (1)

Excavator (2),

Walk Behind compactor (1), 

Fuel truck (1), For buck up

Diesel Generator for crusher(1)


Manpower shortage:-


Structure Forman (1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth Work Forman (1)

Senior lab technician (1)

Chief cook (1)

Office engineering head


Material shortage:


*Black wire 1.5mm

*Rebar Dia 8 & dia 6

*OPC Cement = 400 qtl

*Aggregate 02=4 trucks

*Pipe molds dia 48"=6pcs,only 5 molds 

*Blanket,WC for camp service.

*Cheep wood =50pcs

*Physit= 800pcs


Maintenance (Down Own Equipments)


-Koblelko excavator (Fuel tanker cup & Fuel pump)



Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)


-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Roller (Vibrator Solenoid and pump )


Bottleneck Resources:


*OPC Cement 

*02 Concrete Aggregate

*Unskilled labour /DL/shortage

*Excavator with Jack hammer 

*RC pipe supply ,100m.


Critical issues: 

*Bridge investigation Crew mobilization,

*HIV Subcontractor mobilization

*Traverse and differential data not completed, waiting for yonas chief surveyor


Critical material stock Balance:


Fuel=21,397.06lit, OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=128.00m3,Aggregate 02=0.00m3