DPR
@SerawitGood morning :-23/06/2013
Obora- Sidan- Tuluwayu Road Project;
Daily Work progress:-
Holiday
Working Station from 9+800-22+220
-Common Excavation=400.00m3 with Ex. 3:00hr & Dzr. 0:00 hr
-Common slope trimming=558.52.00m3 with Ex.8:30hr
Intermidate slope trimming=264.06m3 withEx,5:00hr
Intermidate Excavation=1248.00m3 with Ex,13:00
-Mixing & placing=630.00m3 with Gr, 5:30hr
Dumping waste=107.00 trip
HCB work for Engineers house=100.00m2
Masonary work for outlet (pipe culvert)=0.86m3
Pipe production (Dia. 48)=3.00pcs
Pipe Reinforcement (Dia. 48)=11.50 Cage
Executed amount=689,752.08birr
Cost Expense=322,596.10birr
Planned with Avail. Resource=794,850.00birr
Accomp. With Available Resource=86.78%
Cost vs. revenue=46.77%
Machinery Status :- Dozer=5,Grader=1, Excavator=5(1partial down,1down), Loader=2(1down), D.T=13(4down)(5partial down), Fuel truck =1,Water truck =2(1partial down), Vibratory Roller= 2 (2partial idle, AD), Service vehicle =5, Isuzu cargo=1, Isuzu Bus=1
Machinery Shortage:-
Wheel loader(1)
Excavator with jack hammer(1),
Dozer (1)
Excavator (2),
Walk Behind compactor (1),
Fuel truck (1), For buck up
Diesel Generator for crusher(1)
Manpower shortage:-
Structure Forman (1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth Work Forman (1)
Senior lab technician (1)
Chief cook (1)
Office engineering head
Material shortage:
*Black wire 1.5mm
*Rebar Dia 8 & dia 6
*OPC Cement = 400 qtl
*Aggregate 02=4 trucks
*Pipe molds dia 48"=6pcs,only 5 molds
*Blanket,WC for camp service.
*Cheep wood =50pcs
*Physit= 800pcs
Maintenance (Down Own Equipments)
-Koblelko excavator (Fuel tanker cup & Fuel pump)
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Roller (Vibrator Solenoid and pump )
Bottleneck Resources:
*OPC Cement
*02 Concrete Aggregate
*Unskilled labour /DL/shortage
*Excavator with Jack hammer
*RC pipe supply ,100m.
Critical issues:
*Bridge investigation Crew mobilization,
*HIV Subcontractor mobilization
*Traverse and differential data not completed, waiting for yonas chief surveyor
Critical material stock Balance:
Fuel=21,397.06lit, OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=128.00m3,Aggregate 02=0.00m3