Good morning :-20/06/2013 

Obora- Sidan- Tuluwayu Road Project;

 Daily Work progress:-


Working Station from 7+600-22+220


-Common Excavation=7995.00m3 with Ex. 34:30hr & Dzr. 32:30 hr

-Common slope trimming=695.00m3 with Ex.10:00hr

Undercut Excavation=0.00m3 with Ex. 0:00 hr

-Mixing & placing=1162.0m3 with Gr, 9:00hr

-Road bed preparation=0.00 m3  

-Borrow material Prod.=1200.00m3 with Ex,12:00 &Dz,0:00

Dumping waste=236.00 trip

Concrete work for Eng. House=5.15m3

Concrete work for linton(Eng. House)=0.25m3

HCB work for Engineers house=33.00m2

Masonary work for outlet (pipe culvert)=8.70m3

Pipe production (Dia. 48)=4pcs

Pipe Reinforcement (Dia. 48)=14.50 Cage

Executed amount=2,277,300.00birr

Cost Expense=350,477.68birr

Planned with Avail. Resource=2,153,366.67birr

Accomp. With Available Resource=107.22%

Cost vs. revenue=15.39%


Machinery Status :- Dozer=5,Grader=1(partial down), Excavator=5, Loader=2, D.T=13(2down)(3partial down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2partial idle, AD), Service vehicle =5, Isuzu cargo=1

Machinery Shortage:-


Wheel loader(1)

Excavator with jack hammer(1),

Dozer (1)

Excavator (2),

Walk Behind compactor (1), 

Fuel truck (1), For buck up

ISUZU Bus (1)


Manpower shortage:-


Structure Forman (1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth Work Forman (1)

Senior lab technician (1)

Chief cook (1)


Material shortage:


*Black wire 1.5mm

*Rebar Dia 8 & dia 6

*OPC Cement = 400 qtl

*Aggregate 02=4 trucks

*Pipe molds dia 48"=6pcs,only 5 molds 

*Blanket,WC for camp service.

*Cheep wood =50pcs

*Physit= 800pcs


Maintenance (Down Own Equipments)


-Koblelko excavator (Fuel tanker cup &Fuel pump)



Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)


-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Roller (Vibrator Solenoid and pump )

-Dump truck battery


Bottleneck Resources:


*OPC Cement 

*HCB

*Unskilled labour /DL/shortage

*Excavator with Jack hammer 

*RC pipe supply ,100m.

*Mapefluid Accelerator Admixture 


Critical issues: 

*Bridge investigation Crew mobilization,

*HIV Subcontractor mobilization

*Traverse and differential data not completed, waiting for yonas chief surveyor


Critical material stock Balance:


Fuel=33,639.80lit, OPC cement=0.00 Qtl, PPC cement=10.00 Qtl, Sand=64.00m3,Aggregate 02=0.00m3