@SerawitGood morning :-20/06/2013
Obora- Sidan- Tuluwayu Road Project;
Daily Work progress:-
Working Station from 7+600-22+220
-Common Excavation=7995.00m3 with Ex. 34:30hr & Dzr. 32:30 hr
-Common slope trimming=695.00m3 with Ex.10:00hr
Undercut Excavation=0.00m3 with Ex. 0:00 hr
-Mixing & placing=1162.0m3 with Gr, 9:00hr
-Road bed preparation=0.00 m3
-Borrow material Prod.=1200.00m3 with Ex,12:00 &Dz,0:00
Dumping waste=236.00 trip
Concrete work for Eng. House=5.15m3
Concrete work for linton(Eng. House)=0.25m3
HCB work for Engineers house=33.00m2
Masonary work for outlet (pipe culvert)=8.70m3
Pipe production (Dia. 48)=4pcs
Pipe Reinforcement (Dia. 48)=14.50 Cage
Executed amount=2,277,300.00birr
Cost Expense=350,477.68birr
Planned with Avail. Resource=2,153,366.67birr
Accomp. With Available Resource=107.22%
Cost vs. revenue=15.39%
Machinery Status :- Dozer=5,Grader=1(partial down), Excavator=5, Loader=2, D.T=13(2down)(3partial down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2partial idle, AD), Service vehicle =5, Isuzu cargo=1
Machinery Shortage:-
Wheel loader(1)
Excavator with jack hammer(1),
Dozer (1)
Excavator (2),
Walk Behind compactor (1),
Fuel truck (1), For buck up
ISUZU Bus (1)
Manpower shortage:-
Structure Forman (1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth Work Forman (1)
Senior lab technician (1)
Chief cook (1)
Material shortage:
*Black wire 1.5mm
*Rebar Dia 8 & dia 6
*OPC Cement = 400 qtl
*Aggregate 02=4 trucks
*Pipe molds dia 48"=6pcs,only 5 molds
*Blanket,WC for camp service.
*Cheep wood =50pcs
*Physit= 800pcs
Maintenance (Down Own Equipments)
-Koblelko excavator (Fuel tanker cup &Fuel pump)
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Roller (Vibrator Solenoid and pump )
-Dump truck battery
Bottleneck Resources:
*OPC Cement
*HCB
*Unskilled labour /DL/shortage
*Excavator with Jack hammer
*RC pipe supply ,100m.
*Mapefluid Accelerator Admixture
Critical issues:
*Bridge investigation Crew mobilization,
*HIV Subcontractor mobilization
*Traverse and differential data not completed, waiting for yonas chief surveyor
Critical material stock Balance:
Fuel=33,639.80lit, OPC cement=0.00 Qtl, PPC cement=10.00 Qtl, Sand=64.00m3,Aggregate 02=0.00m3