Good morning :-18/06/2013 

Obora- Sidan- Tuluwayu Road Project;

 Daily Work progress:-


Working Station from 5+160-22+220


-Common Excavation=6060.00m3 with Ex. 20:00hr & Dzr. 24:30 hr

-Common slope trimming=1116.88m3 with Ex.10:00hr

Undercut Excavation=1170.00m3 with Ex. 10:30 hr

-Mixing & placing=1352.40m3 with Gr,10:30 hr

-Road bed preparation=0.00 m3  

-Borrow material Prod.=1000.00m3 withEx,10:00

Dumping waste=204.00 trip

Concrete work for Eng. House=8.87m3

HCB work for Engineers house=73.00m2

Masonary work for outlet (pipe culvert)=1.83m3

Pipe production (Dia. 48)=3pcs

pipe Reinforcement (Dia. 48)=13.50 Cage

Executed amount=2,209,760.00birr

Cost Expense=423,327.79 birr

Planned with Avail. Resource=1,672,050.00birr

Accomp. With Available Resource=132.16%

Cost vs. revenue=19.16%


Machinery Status :- Dozer=5(2Down(1 Own)),Grader=1, Excavator=5(1partial down(own)), Loader=2, D.T=13(1down)(3 partial down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2 idle, AD), Service vehicle =4 , Isuzu cargo=1


Machinery Shortage:-

Wheel loader(1)

Excavator with jack hammer(1),

Dozer (1)

Excavator(2),

Walk Behind compactor (1), 

Small Service Vehicle (1)

Fuel truck (1), For buck up

ISUZU Bus (1)


Manpower shortage:-

Supper Intendent (1)

Structure Forman(1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth Work Forman (1)

Senior lab technician (1)

Chief cook (1)


Material shortage:


*Rebar Dia 8 & dia 6

*OPC Cement = 200 qtl

*Aggregate 02=4 trucks

*Pipe molds dia 48"=6pcs,only 4 molds are working, others need maintenance

*General staff Bed, Blanket,WC for camp service.

*Cheep wood =50pcs

*Physit= 800pcs


Maintenance (Down Own Equipments)


-Koblelko excavator (Fuel tanker cup)


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)


-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Roller (vibrator and pump )

-750 lit mixer (cabo)

-Dump truck battery

-Maintenance mechanic (for fuel truck dispensor counter error in counting), 


Bottleneck Resources:


*HCB

*Unskilled labour /DL/shortage

*Excavator with Jack hammer 

*RC pipe supply ,100m


Critical issues: 

*Bridge investigation Crew mobilization,

*HIV Subcontractor mobilization

*Traverse and differential data not completed, waiting for yonas chief surveyor

Critical material stock Balance:


Fuel=45,152.72 lit, OPC cement=195.00 Qtl, PPC cement=144.00 Qtl, Sand=48.00m3,Aggregate 02=48.00m3