DPR
@SerawitGood morning :-18/06/2013
Obora- Sidan- Tuluwayu Road Project;
Daily Work progress:-
Working Station from 5+160-22+220
-Common Excavation=6060.00m3 with Ex. 20:00hr & Dzr. 24:30 hr
-Common slope trimming=1116.88m3 with Ex.10:00hr
Undercut Excavation=1170.00m3 with Ex. 10:30 hr
-Mixing & placing=1352.40m3 with Gr,10:30 hr
-Road bed preparation=0.00 m3
-Borrow material Prod.=1000.00m3 withEx,10:00
Dumping waste=204.00 trip
Concrete work for Eng. House=8.87m3
HCB work for Engineers house=73.00m2
Masonary work for outlet (pipe culvert)=1.83m3
Pipe production (Dia. 48)=3pcs
pipe Reinforcement (Dia. 48)=13.50 Cage
Executed amount=2,209,760.00birr
Cost Expense=423,327.79 birr
Planned with Avail. Resource=1,672,050.00birr
Accomp. With Available Resource=132.16%
Cost vs. revenue=19.16%
Machinery Status :- Dozer=5(2Down(1 Own)),Grader=1, Excavator=5(1partial down(own)), Loader=2, D.T=13(1down)(3 partial down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2 idle, AD), Service vehicle =4 , Isuzu cargo=1
Machinery Shortage:-
Wheel loader(1)
Excavator with jack hammer(1),
Dozer (1)
Excavator(2),
Walk Behind compactor (1),
Small Service Vehicle (1)
Fuel truck (1), For buck up
ISUZU Bus (1)
Manpower shortage:-
Supper Intendent (1)
Structure Forman(1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth Work Forman (1)
Senior lab technician (1)
Chief cook (1)
Material shortage:
*Rebar Dia 8 & dia 6
*OPC Cement = 200 qtl
*Aggregate 02=4 trucks
*Pipe molds dia 48"=6pcs,only 4 molds are working, others need maintenance
*General staff Bed, Blanket,WC for camp service.
*Cheep wood =50pcs
*Physit= 800pcs
Maintenance (Down Own Equipments)
-Koblelko excavator (Fuel tanker cup)
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Roller (vibrator and pump )
-750 lit mixer (cabo)
-Dump truck battery
-Maintenance mechanic (for fuel truck dispensor counter error in counting),
Bottleneck Resources:
*HCB
*Unskilled labour /DL/shortage
*Excavator with Jack hammer
*RC pipe supply ,100m
Critical issues:
*Bridge investigation Crew mobilization,
*HIV Subcontractor mobilization
*Traverse and differential data not completed, waiting for yonas chief surveyor
Critical material stock Balance:
Fuel=45,152.72 lit, OPC cement=195.00 Qtl, PPC cement=144.00 Qtl, Sand=48.00m3,Aggregate 02=48.00m3