@SerawitGood morning :-17/06/2013
Obora- Sidan- Tuluwayu Road Project;
Daily Work progress:-
Working Station from 7+580-22+220
-Common Excavation=6360.00m3 with Ex. 22:30hr & Dzr. 28:30 hr
-Common slope trimming=1401.31m3 with Ex.13:30hr
Undercut Excavation=810.00m3 with Ex. 7:30 hr
-Mixing & placing=1148.00m3 with Gr,10:10 hr
-Road bed preparation=0.00 m3
-Borrow material Prod.=700.00m3 withEx,7:00
Dumping waste=228.00 trip
Stone Dressing=0.00 pcs
Concrete work for Eng. House=5.58m3
HCB work for Engineers house=25.00m2
Masonary work for outlet (pipe culvert)=3.51m3
Pipe production (Dia. 48)=2pcs
pipe Reinforcement (Dia. 48)=10 Cage
Executed amount=2,238,495.00birr
Cost Expense=419,874.04 birr
Planned with Avail. Resource=1,859,433.33birr
Accomp. With Available Resource=120.39%
Cost vs. revenue=18.76%
Machinery Status :- Dozer=5(2Down(1Own)),Grader=1, Excavator=5(1partial down(own)), Loader=1, D.T=13(3down)(3 partial down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2 idle, AD), Service vehicle =4 , Isuzu=1(down,rental)
Machinery Shortage:-
Wheel loader(1)
Excavator with jack hammer(1),
Dozer (1)
Excavator(2),
Walk Behind compactor (1),
Small Service Vehicle (1)
Fuel truck (1), For buck up
ISUZU Bus (1)
Manpower shortage:-
Supper Intendent (1)
Structure Forman(1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth Work Forman (1)
Senior lab technician (1)
Chief cook (1)
Material shortage:
*OPC Cement = 200 qtl
*Aggregate 02=62m3
*Pipe molds dia 48"=6pcs,only 4 molds are working, others need maintenance
*General staff Bed, Blanket,WC for camp service.
*Cheep wood =50pcs
*Physit= 800pcs
Maintenance (Down Own Equipments)
-Koblelko excavator (Fuel tanker cup)
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Roller (vibrator and pump )
-750 lit mixer (cabo)
-Dump truck battery
-Excavator fuel tanker CUP
-Maintenance mechanic (for fuel truck dispensor counter error in counting),
Bottleneck Resources:
*Cement
*HCB
*unskilled labour /DL/shortage
*Jack hammer
*RC pipe supply
*Fuel Supply interruption
Critical issues:
*Installation of 2nd fuel tanker,
*Bridge investigation Crew mobilization,
*HIV Subcontractor mobilization
Critical material stock Balance:
Fuel=50,844.18 lit, OPC cement=195.00 Qtl, PPC cement=144.00 Qtl, Sand=16.00m3,Aggregate 02=28.00m3