DPR

DPR

@Serawit



Good morning :-17/06/2013 

Obora- Sidan- Tuluwayu Road Project;

 Daily Work progress:-


Working Station from 7+580-22+220


-Common Excavation=6360.00m3 with Ex. 22:30hr & Dzr. 28:30 hr

-Common slope trimming=1401.31m3 with Ex.13:30hr

Undercut Excavation=810.00m3 with Ex. 7:30 hr

-Mixing & placing=1148.00m3 with Gr,10:10 hr

-Road bed preparation=0.00 m3  

-Borrow material Prod.=700.00m3 withEx,7:00

Dumping waste=228.00 trip

Stone Dressing=0.00 pcs

Concrete work for Eng. House=5.58m3

HCB work for Engineers house=25.00m2

Masonary work for outlet (pipe culvert)=3.51m3

Pipe production (Dia. 48)=2pcs

pipe Reinforcement (Dia. 48)=10 Cage

Executed amount=2,238,495.00birr

Cost Expense=419,874.04 birr

Planned with Avail. Resource=1,859,433.33birr

Accomp. With Available Resource=120.39%

Cost vs. revenue=18.76%


Machinery Status :- Dozer=5(2Down(1Own)),Grader=1, Excavator=5(1partial down(own)), Loader=1, D.T=13(3down)(3 partial down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2 idle, AD), Service vehicle =4 , Isuzu=1(down,rental)


Machinery Shortage:-

Wheel loader(1)

Excavator with jack hammer(1),

Dozer (1)

Excavator(2),

Walk Behind compactor (1), 

Small Service Vehicle (1)

Fuel truck (1), For buck up

ISUZU Bus (1)


Manpower shortage:-

Supper Intendent (1)

Structure Forman(1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth Work Forman (1)

Senior lab technician (1)

Chief cook (1)


Material shortage:


*OPC Cement = 200 qtl

*Aggregate 02=62m3

*Pipe molds dia 48"=6pcs,only 4 molds are working, others need maintenance

*General staff Bed, Blanket,WC for camp service.

*Cheep wood =50pcs

*Physit= 800pcs


Maintenance (Down Own Equipments)


-Koblelko excavator (Fuel tanker cup)


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)

-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Roller (vibrator and pump )

-750 lit mixer (cabo)

-Dump truck battery

-Excavator fuel tanker CUP

-Maintenance mechanic (for fuel truck dispensor counter error in counting), 


Bottleneck Resources:


*Cement

*HCB

*unskilled labour /DL/shortage

*Jack hammer

*RC pipe supply 

*Fuel Supply interruption


Critical issues: 

*Installation of 2nd fuel tanker, 

*Bridge investigation Crew mobilization,

*HIV Subcontractor mobilization


Critical material stock Balance:


Fuel=50,844.18 lit, OPC cement=195.00 Qtl, PPC cement=144.00 Qtl, Sand=16.00m3,Aggregate 02=28.00m3