Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-



Working Station from 6+420-46+600


-Common Excavation=5186.40m3 with Ex. 19:00hr Dz.13:00

-Common slope trimming=1395.75m3 with Ex.14:30hr

-Clearing & Grubbing=4.20 hect. With Dzr 14:00 hr

-Mixing & placing=630.00m3 with Gr. 7:30 hr

-Road bed preparation=0.00m3 

-Borrow material Prod.=0.00m3 

Dumping waste=110.00 trip

Concrete work for Eng. House=4.25 m3

HCB for engineers house =16m3

Excavation for pipe culvert=0.00m3

lean concrete for pipe culvert=0.44 m3

Executed amount=2,306,391.00birr

Cost Expense=382,753.30birr

Planned with Avail. Resource=1,881,700.00birr

Accomp. With Available Resource=122.57%

Cost vs. revenue=16.60%


Machinery Status :- Dozer=5(1Down(Own)) ,Grader=1(partial down),Excavator=5(1partial down), Loader=1, D.T=13(3 down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2 idle, AD), Service vehicle =4, Isuzu=1(down,rental)


Machinery Shortage:-

Wheel loader(2)

Excavator with jack hammer(1),

Dozer (1)

Excavator(2),

Walk behind compactor (1), 

Small Service Vehicle (1)

Fuel truck (1), For buck up

ISUZU Bus (1)


Manpower shortage:-

Supper Intendent (1)

Structure Forman(2),

Equipment Maintenance Forman(1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth work Forman (1)


Material shortage:


*OPC Cement = 200 qtl

*Aggregate 02=48m3

*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance

*General staff Bed, Blanket,WC for camp service.

*Cheep wood =50pcs

*Physist=800pcs


Maintenance (Down Own Equipments

-Roller (vibrator and pump )


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)

-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Maintenance mechanic (for fuel truck dispensor counter error in counting), 


Bottleneck Resources:


*Cement

*HCB

*unskilled labour shortage, project is working hard on it.

*Shortage of loaders, As we are obliged to use dozer for waste pushing

*Jack hammer, it is hurting work continuity of stretches

*Fuel Supply interruption


Critical issues: 

*Installation of 2nd fuel tanker, 

*Bridge investigation Crew mobilization, the two bridges are now accessible

*HIV Subcontractor mobilization



Critical material stock Balance:


Fuel=22,104.99lit , OPC cement=250.00 Qtl, PPC cement=185.00 Qtl, Sand=48.00m3,Aggregate 02=56.00m3