Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-
Working Station from 6+420-46+600
-Common Excavation=5186.40m3 with Ex. 19:00hr Dz.13:00
-Common slope trimming=1395.75m3 with Ex.14:30hr
-Clearing & Grubbing=4.20 hect. With Dzr 14:00 hr
-Mixing & placing=630.00m3 with Gr. 7:30 hr
-Road bed preparation=0.00m3
-Borrow material Prod.=0.00m3
Dumping waste=110.00 trip
Concrete work for Eng. House=4.25 m3
HCB for engineers house =16m3
Excavation for pipe culvert=0.00m3
lean concrete for pipe culvert=0.44 m3
Executed amount=2,306,391.00birr
Cost Expense=382,753.30birr
Planned with Avail. Resource=1,881,700.00birr
Accomp. With Available Resource=122.57%
Cost vs. revenue=16.60%
Machinery Status :- Dozer=5(1Down(Own)) ,Grader=1(partial down),Excavator=5(1partial down), Loader=1, D.T=13(3 down), Fuel truck =1,Water truck =2, Vibratory Roller= 2 (2 idle, AD), Service vehicle =4, Isuzu=1(down,rental)
Machinery Shortage:-
Wheel loader(2)
Excavator with jack hammer(1),
Dozer (1)
Excavator(2),
Walk behind compactor (1),
Small Service Vehicle (1)
Fuel truck (1), For buck up
ISUZU Bus (1)
Manpower shortage:-
Supper Intendent (1)
Structure Forman(2),
Equipment Maintenance Forman(1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth work Forman (1)
Material shortage:
*OPC Cement = 200 qtl
*Aggregate 02=48m3
*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance
*General staff Bed, Blanket,WC for camp service.
*Cheep wood =50pcs
*Physist=800pcs
Maintenance (Down Own Equipments
-Roller (vibrator and pump )
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Maintenance mechanic (for fuel truck dispensor counter error in counting),
Bottleneck Resources:
*Cement
*HCB
*unskilled labour shortage, project is working hard on it.
*Shortage of loaders, As we are obliged to use dozer for waste pushing
*Jack hammer, it is hurting work continuity of stretches
*Fuel Supply interruption
Critical issues:
*Installation of 2nd fuel tanker,
*Bridge investigation Crew mobilization, the two bridges are now accessible
*HIV Subcontractor mobilization
Critical material stock Balance:
Fuel=22,104.99lit , OPC cement=250.00 Qtl, PPC cement=185.00 Qtl, Sand=48.00m3,Aggregate 02=56.00m3