Good morning :-11/06/2013

Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-



Working Station from 1+660-45+400


-Common Excavation=2307.50m3 with Ex. 25:45 hr

-Common slope trimming=616.88m3 with Ex.7:15hr

-Clearing & Grubbing=3.85 hect. With Dzr 19:00 hr

-Mixing & placing=266.00m3 with Gr. 6:00 hr

-Road bed preparation=0.00m3 

-Borrow material Prod.=0.00m3 

Dumping waste=178.00 trip

Concrete work for column Eng. House=1.20 m3

Excavation for pipe culvert=0.00m3

lean concrete for pipe culvert=0.44

Executed amount=1,765,430.00birr

Cost Expense=407,690.63birr

Planned with Avail. Resource=1,816,950.00birr

Accomp. With Available Resource=97.16%

Cost vs. revenue=23.09%


Machinery Status :- Dozer=5(1Down(Own)) ,Grader=1,Excavator=5, Loader=1, D.T=13(3 down)&4(AD), Fuel truck =1,Water truck =2(2AD), Vibratory Roller= 2 (2AD), Service vehicle =4(1 Down own), Isuzu=1(down,rental)


Machinery Shortage:-

Wheel loader(2)

Excavator with jack hammer(1),

Dozer (1)

Excavator(2),

Walk behind compactor (1), 

Small Service Vehicle (1)

Fuel truck (1), For buck up

ISUZU Bus (1)


Manpower shortage:-

Supper Intendent (1)

Structure Forman(2),

Equipment Maintenance Forman(1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth work Forman (1)


Material shortage:


*OPC Cement = 300 qtl

*Aggregate 02=62m3

*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance

*General staff Bed, Blanket,WC for camp service.


Maintenance (Down Own Equipments)

-Double cab pick up (Gear and lock problem)

-Roller (vibrator and pump )

-750 lit Concrete mixer -Motor support


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)

-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Maintenance mechanic (for fuel truck dispensor counter error in counting), 


Bottleneck Resources:


*Cement

*HCB

*Bar benders and unskilled labour shortage, project is working hard on it.

*Shortage of loaders, As we are obliged to use dozer for waste pushing

*Jack hammer, it is hurting work continuity of stretches

*Fuel Supply interruption


Critical issues: 

*Installation of 2nd fuel tanker, 

*Bridge investigation Crew mobilization, the two bridges are now accessible

*HIV Subcontractor mobilization



Critical material stock Balance:


Fuel=27,028.42lit , OPC cement=0.00 Qtl, PPC cement=200.00 Qtl, Sand=48.00m3,Aggregate 02=56.00m3