Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-
Working Station from 1+660-45+400
-Common Excavation=2307.50m3 with Ex. 25:45 hr
-Common slope trimming=616.88m3 with Ex.7:15hr
-Clearing & Grubbing=3.85 hect. With Dzr 19:00 hr
-Mixing & placing=266.00m3 with Gr. 6:00 hr
-Road bed preparation=0.00m3
-Borrow material Prod.=0.00m3
Dumping waste=178.00 trip
Concrete work for column Eng. House=1.20 m3
Excavation for pipe culvert=0.00m3
lean concrete for pipe culvert=0.44
Executed amount=1,765,430.00birr
Cost Expense=407,690.63birr
Planned with Avail. Resource=1,816,950.00birr
Accomp. With Available Resource=97.16%
Cost vs. revenue=23.09%
Machinery Status :- Dozer=5(1Down(Own)) ,Grader=1,Excavator=5, Loader=1, D.T=13(3 down)&4(AD), Fuel truck =1,Water truck =2(2AD), Vibratory Roller= 2 (2AD), Service vehicle =4(1 Down own), Isuzu=1(down,rental)
Machinery Shortage:-
Wheel loader(2)
Excavator with jack hammer(1),
Dozer (1)
Excavator(2),
Walk behind compactor (1),
Small Service Vehicle (1)
Fuel truck (1), For buck up
ISUZU Bus (1)
Manpower shortage:-
Supper Intendent (1)
Structure Forman(2),
Equipment Maintenance Forman(1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Earth work Forman (1)
Material shortage:
*OPC Cement = 300 qtl
*Aggregate 02=62m3
*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance
*General staff Bed, Blanket,WC for camp service.
Maintenance (Down Own Equipments)
-Double cab pick up (Gear and lock problem)
-Roller (vibrator and pump )
-750 lit Concrete mixer -Motor support
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Maintenance mechanic (for fuel truck dispensor counter error in counting),
Bottleneck Resources:
*Cement
*HCB
*Bar benders and unskilled labour shortage, project is working hard on it.
*Shortage of loaders, As we are obliged to use dozer for waste pushing
*Jack hammer, it is hurting work continuity of stretches
*Fuel Supply interruption
Critical issues:
*Installation of 2nd fuel tanker,
*Bridge investigation Crew mobilization, the two bridges are now accessible
*HIV Subcontractor mobilization
Critical material stock Balance:
Fuel=27,028.42lit , OPC cement=0.00 Qtl, PPC cement=200.00 Qtl, Sand=48.00m3,Aggregate 02=56.00m3