DPR

DPR

@Serawit

Good morning :-10/06/2013

Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-



Working Station from 1+820-43+700


-Common Excavation=5223.19.00m3 with Ex. 30:00 hr & Dz.13:00 hr

-Common slope trimming=795.00m3m3 with Ex.11:00 hr

-Clearing & Grubbing=3.60 hect. With Dzr 16:00 hr

-Mixing & placing=742.00m3 eith Gr. 11:30 hr

-Road bed preparstion=0.00m3 with Gr. 0:00 hr

-Borrow material Prod.=400.00m3 with Ex. 4:00 hr

Dumping waste=181.00 trip

Concrete work for column Eng. House=0.67 m3

Excavation for pipe culvert=4.25m3

Executed amount=2,104,165.60birr

Cost Expense=425,714.05birr

Planned with Avail. Resource=1,957,266.07birr

Accomp. With Available Resource=107.51%

Cost vs. revenue=20.23%


Machinery Status :- Dozer=5(1Down(Own)) ,Grader=1(partial down),Excavator=5(2partial down), Loader=1, D.T=13(6 down), Fuel truck =1,Water truck =2(2AD), Vibratory Roller= 2 (1Down&1AD), Service vehicle =4(1 Down own), Isuzu=1(down,rental)


Machinery Shortage:-

Wheel loader(2)

Excavator with jack hammer(1),

Dozer (1)

Excavator(2),

Walk behind compactor (1), 

Small Service Vehicle (1)

Fuel truck (1), For buck up

ISUZU Bus (1)


Manpower shortage:-

Supper Intendent (1)

Structure Forman(2),

Equipment Maintenance Forman(1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)

Earth work Forman (1)


Material shortage:


*OPC Cement = 300 qtl

*Aggregate 02=62m3

*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance

*General staff Bed, Blanket,WC for camp service.


Maintenance (Down Own Equipments)

-Double cab pick up (Gear and lock problem)

-Roller (vibrator and pump )

-750 lit Concrete mixer -Motor support


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)

-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Maintenance mechanic (for fuel truck dispensor counter error in counting), 


Bottleneck Resources:


*Cement

*HCB

*Bar benders and unskilled labour shortage, project is working hard on it.

*Shortage of loaders, As we are obliged to use dozer for waste pushing

*Jack hammer, it is hurting work continuity of stretches

*Fuel Supply interruption


Critical issues: 

*Installation of 2nd fuel tanker, 

*Bridge investigation Crew mobilization, the two bridges are now accessible

*HIV Subcontractor mobilization



Critical material stock Balance:


Fuel=31,727.86lit , OPC cement=0.00 Qtl, PPC cement=0.00 Qtl, Sand=48.00m3,Aggregate 02=56.00m3