Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-


Working Station from 3+797-41+300


Common Excavation=3793.51m3

Common slope trimming=340.00m3

Clearing & Grubbing=1.80 hect.

Mixing & placing=350.00m3

Road bed preparstion=440.00m3

Concrete work for Eng. House=8.69m3

Masonary work for pipe culvert=1.70m3

Executed amount=1,392,767.40 birr

Cost Expense=366,050.48 birr

Planned with Avail. Resource=1,501,325.00birr

Accomp. With Available Resource=92.77%

Cost vs. revenue=26.28%


Machinery Status :- Dozer=5(1Down/1Own)) ,Grader=1,Excavator=5, Loader=1, D.T=13(5 partial down), Fuel truck =1,Water truck =2(1 down/1 own left the project), Vibratory Roller= 2 (1 idle;AD) (1 Down/1 Own), Service vehicle =4(1 Down/1 own), 750 liter concrete mixer=1 (1 down)

Isuzu=1(1down/1rental)


Machinery Shortage:-

Water truck(1)

Wheel loader(2)

Excavator with jack hammer(1),

Dozer (1)

Excavator(2),

Walk behind compactor (1), 

Small Service Vehicle (1)

Fuel truck (1), For buck up


Manpower shortage:-

Supper Intendent (1)

Structure Forman(2),

Equipment Maintenance Forman(1),

Project Finance Head (1)

Plumber (1), 

Structural /site/ engineer (1)


Material shortage:


*Fuel 50,000lit

*OPC Cement = 300 qtl

*Aggregate 02=62m3

*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance

*GIS,As per the monthly resources plan

*General staff Bed, Blanket,WC for camp service


Maintenance (Down Own Equipments)

-Double cab pick up (Gear and lock problem)

-Roller (Oring seal and vibrator )

-Concrete mixer -Motor support


Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)

-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)

-Maintenance mechanic (for fuel truck dispensor counter error in counting), 


Bottleneck Resources:


*02 Concrete aggregate

*Mobilization of one water truck

*Bar benders and unskilled labour shortage, project is working hard on it.

*Shortage of loaders, As we are obliged to use dozer for waste pushing

*Jack hammer, it is hurting work continuity of stretches

*Fuel Supply interruption

*Cement 


Critical issues: 

*Installation of 2nd fuel tanker, 

*Bridge investigation Crew mobilization, the two bridges are now accessible

*HIV Subcontractor mobilization



Critical material stock Balance:


Fuel=93.72lit, OPC cement=146.00 Qtl, PPC cement=0.00 Qtl, Sand=0.00m3,Aggregate 02=48.00m3