DPR
@SerawitGood morning :-06/06/2013
Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-
Working Station from 3+797-41+300
Common Excavation=3793.51m3
Common slope trimming=340.00m3
Clearing & Grubbing=1.80 hect.
Mixing & placing=350.00m3
Road bed preparstion=440.00m3
Concrete work for Eng. House=8.69m3
Masonary work for pipe culvert=1.70m3
Executed amount=1,392,767.40 birr
Cost Expense=366,050.48 birr
Planned with Avail. Resource=1,501,325.00birr
Accomp. With Available Resource=92.77%
Cost vs. revenue=26.28%
Machinery Status :- Dozer=5(1Down/1Own)) ,Grader=1,Excavator=5, Loader=1, D.T=13(5 partial down), Fuel truck =1,Water truck =2(1 down/1 own left the project), Vibratory Roller= 2 (1 idle;AD) (1 Down/1 Own), Service vehicle =4(1 Down/1 own), 750 liter concrete mixer=1 (1 down)
Isuzu=1(1down/1rental)
Machinery Shortage:-
Water truck(1)
Wheel loader(2)
Excavator with jack hammer(1),
Dozer (1)
Excavator(2),
Walk behind compactor (1),
Small Service Vehicle (1)
Fuel truck (1), For buck up
Manpower shortage:-
Supper Intendent (1)
Structure Forman(2),
Equipment Maintenance Forman(1),
Project Finance Head (1)
Plumber (1),
Structural /site/ engineer (1)
Material shortage:
*Fuel 50,000lit
*OPC Cement = 300 qtl
*Aggregate 02=62m3
*Pipe molds dia 48"=6pcs,only two molds are working, others need maintenance
*GIS,As per the monthly resources plan
*General staff Bed, Blanket,WC for camp service
Maintenance (Down Own Equipments)
-Double cab pick up (Gear and lock problem)
-Roller (Oring seal and vibrator )
-Concrete mixer -Motor support
Critical Maintenance items /spare parts (for Own equipments working with remarks ,WWR)
-3- 57459 Fuel truck (Tyre 12*20 RR=8, Tyre 12*20 FR =2)
-Maintenance mechanic (for fuel truck dispensor counter error in counting),
Bottleneck Resources:
*02 Concrete aggregate
*Mobilization of one water truck
*Bar benders and unskilled labour shortage, project is working hard on it.
*Shortage of loaders, As we are obliged to use dozer for waste pushing
*Jack hammer, it is hurting work continuity of stretches
*Fuel Supply interruption
*Cement
Critical issues:
*Installation of 2nd fuel tanker,
*Bridge investigation Crew mobilization, the two bridges are now accessible
*HIV Subcontractor mobilization
Critical material stock Balance:
Fuel=93.72lit, OPC cement=146.00 Qtl, PPC cement=0.00 Qtl, Sand=0.00m3,Aggregate 02=48.00m3