DPR
AbinaelGood morning :-28/04/2013
Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-
Working Station from 4+900- 24+860
Common Excavation=1732.50m3
common slope trimming=477.81m3
Clearing & Grubbing=2.08 hect.
Road bed Preparation=0.00m3
Under cut Excavation=744.00m3
Mixing & placing=1096.00m3
Borrow material Prod.=1050.00m3
masonry work (consultant house)=5.65 m3
Pipe Reinforcement=162.2Kg
Pipe Production ❨Dia.48)=1.00pcs
Executed amount=1,185,435.00 birr
Cost(Expense) =285,058.87 birr
Planned with Avail. Resource=1,275,451.67 birr
With Available Resource=92.94%
Cost vs. revenue=24.05%
Machinery Status :- Dozer=4,Grader=1,Excavator=3, Loader=1, D.T=4, Fuel truck 1, Water truck 1, Vibratory Roller= 2, Service vehicle =4
Machinery Shortage:-Dozer (2), Dump truck(8), Wheel loader(1),Water truck(1), Vibrator Roller 16T (1), Isuzu cargo (1), Excavator(4), Excavator with jack hammer(1), walk behind compactor (1),Water pump 4" benzine running (2), Concrete mixer 750 lit (1)
Manpower shortage:-
*Structure Forman(2), Plumber (1), Maintenance Forman.
Material shortage:
*OPC Cement = 200 qtl
*10w Hydraulic oil = 1 barrel
*Pipe molds dia 48"=11 pcs
Maintenance (Down Own Equipments)
-Roller (Vibration problem), working with remark
Critical Maintenance items /spare parts (for Own equipments)
-Sino truck bolt with nut 20 PCs
-Tyre with inner tube for the double pick up
-End bit, riper tip, fuel filter ,oil filter, cutting edge for komatsu's dozer
-Air Compressor steel hoze
-Service elements for the two kobeleco excavators
-Service elements for the vibrator roller
Critical issues:
*Mobilization of the chief surveyor/ yonas/ for documentation works
*Remaining lab equipments , as per the request
*Food budget for Tir 2013
Critical material stock Balance:
Fuel=47,577.81 lit , OPC cement=19.00 Qtl, PPC cement=100.00 Qtl, Sand=00.00m3,Aggregate 02=00.00m3