DPR

DPR

Abinael

Good morning :-28/04/2013

Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-


Working Station from 4+900- 24+860


Common Excavation=1732.50m3

common slope trimming=477.81m3

Clearing & Grubbing=2.08 hect.

Road bed Preparation=0.00m3

Under cut Excavation=744.00m3

Mixing & placing=1096.00m3

Borrow material Prod.=1050.00m3

masonry work (consultant house)=5.65 m3

Pipe Reinforcement=162.2Kg

Pipe Production ❨Dia.48)=1.00pcs

Executed amount=1,185,435.00 birr

Cost(Expense) =285,058.87 birr

Planned with Avail. Resource=1,275,451.67 birr

With Available Resource=92.94%

Cost vs. revenue=24.05%


Machinery Status :- Dozer=4,Grader=1,Excavator=3, Loader=1, D.T=4, Fuel truck 1, Water truck 1, Vibratory Roller= 2, Service vehicle =4


Machinery Shortage:-Dozer (2), Dump truck(8), Wheel loader(1),Water truck(1), Vibrator Roller 16T (1), Isuzu cargo (1), Excavator(4), Excavator with jack hammer(1), walk behind compactor (1),Water pump 4" benzine running (2), Concrete mixer 750 lit (1)


Manpower shortage:-

*Structure Forman(2), Plumber (1), Maintenance Forman.


Material shortage:

*OPC Cement = 200 qtl

*10w Hydraulic oil = 1 barrel

*Pipe molds dia 48"=11 pcs


Maintenance (Down Own Equipments)

-Roller (Vibration problem), working with remark



Critical Maintenance items /spare parts (for Own equipments)

-Sino truck bolt with nut 20 PCs

-Tyre with inner tube for the double pick up

-End bit, riper tip, fuel filter ,oil filter, cutting edge for komatsu's dozer

-Air Compressor steel hoze

-Service elements for the two kobeleco excavators

-Service elements for the vibrator roller



Critical issues: 

*Mobilization of the chief surveyor/ yonas/ for documentation works 

*Remaining lab equipments , as per the request

*Food budget for Tir 2013


Critical material stock Balance:


Fuel=47,577.81 lit , OPC cement=19.00 Qtl, PPC cement=100.00 Qtl, Sand=00.00m3,Aggregate 02=00.00m3