DPR

DPR

@Abinael

Good morning :-27/04/2013

Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-


Working Station from 4+500- 24+340


Common Excavation=992.0m3

common slope trimming=412.50m3

Clearing & Grubbing=1.76 hect.

Road bed Preparation=360.00m3

masonry work (consultant house)=6.75m3

Pipe Reinforcement=100.8Kg

Under cut Excabation=532.80m3

Executed amount=748,752.00birr

Cost(Expense) =288,793.01 birr

Planned with Available Resource=1,043,616.67 birr

With Available Resource=71.75%

Cost vs. revenue=38.57%


Machinery Status :- Dozer=4(2down),Grader=1,Excavator=3, Loader=1, D.T=4, Fuel truck 1, Water truck 1, Vibratory Roller= 2, Service vehicle =4


Machinery Shortage:-Dozer (2), Dump truck(9), Wheel loader(1),Water truck(1), Vibrator Roller 16T (1), Isuzu cargo (1), Excavator(4), Excavator with jack hammer(1), walk behind compactor (1),Water pump 4" benzine running (2), walk behind compactor 1)


Manpower shortage:-

*Structure Forman(2), Plumber (1), Maintenance Forman.


Material shortage:

*OPC Cement = 200 qtl

*10w Hydraulic oil = 1 barrel

*Pipe molds dia 48"=11 pcs


Maintenance (Down Own Equipments)

-Roller (Vibration problem), working with remark



Critical Maintenance items /spare parts (for Own equipments)

-Sino truck bolt with nut 20 PCs

-Tyre with inner tube for the double pick up

-End bit, riper tip, fuel filter ,oil filter, cutting edge for komatsu's dozer

-Air Compressor steel hoze

-Service elements for the two kobeleco excavators

-Service elements for the vibrator roller



Critical issues: 

*The chief surveyor yonas/ documentation works 

*Remaining lab equipments , as per the request


Critical material stock Balance:


Fuel=50,849 lit(Received=46,377.08 lit), OPC cement=19.00 Qtl, PPC cement=126.00 Qtl, Sand=00.00m3,Aggregate 02=00.00m3

Report Page