DPR
AbinaelGood morning :-27/04/2013
Obora- Sidan- Tuluwayu Road Project;- Daily Work progress:-
Working Station from 4+500- 24+340
Common Excavation=992.0m3
common slope trimming=412.50m3
Clearing & Grubbing=1.76 hect.
Road bed Preparation=360.00m3
masonry work (consultant house)=6.75m3
Pipe Reinforcement=100.8Kg
Under cut Excabation=532.80m3
Executed amount=748,752.00birr
Cost(Expense) =288,793.01 birr
Planned with Available Resource=1,043,616.67 birr
With Available Resource=71.75%
Cost vs. revenue=38.57%
Machinery Status :- Dozer=4(2down),Grader=1,Excavator=3, Loader=1, D.T=4, Fuel truck 1, Water truck 1, Vibratory Roller= 2, Service vehicle =4
Machinery Shortage:-Dozer (2), Dump truck(9), Wheel loader(1),Water truck(1), Vibrator Roller 16T (1), Isuzu cargo (1), Excavator(4), Excavator with jack hammer(1), walk behind compactor (1),Water pump 4" benzine running (2), walk behind compactor 1)
Manpower shortage:-
*Structure Forman(2), Plumber (1), Maintenance Forman.
Material shortage:
*OPC Cement = 200 qtl
*10w Hydraulic oil = 1 barrel
*Pipe molds dia 48"=11 pcs
Maintenance (Down Own Equipments)
-Roller (Vibration problem), working with remark
Critical Maintenance items /spare parts (for Own equipments)
-Sino truck bolt with nut 20 PCs
-Tyre with inner tube for the double pick up
-End bit, riper tip, fuel filter ,oil filter, cutting edge for komatsu's dozer
-Air Compressor steel hoze
-Service elements for the two kobeleco excavators
-Service elements for the vibrator roller
Critical issues:
*The chief surveyor yonas/ documentation works
*Remaining lab equipments , as per the request
Critical material stock Balance:
Fuel=50,849 lit(Received=46,377.08 lit), OPC cement=19.00 Qtl, PPC cement=126.00 Qtl, Sand=00.00m3,Aggregate 02=00.00m3